Issue 42-4Vol 42 · Issue 4Issue 42-3Vol 42 · Issue 3Issue 42-2Vol 42 · Issue 2Issue 42-1Vol 42 · Issue 1Issue 41-6Vol 41 · Issue 6Issue 41-5Vol 41 · Issue 5Issue 41-4Vol 41 · Issue 4Issue 41-3Vol 41 · Issue 3Issue 41-2Vol 41 · Issue 2Issue 41-1Vol 41 · Issue 1Issue 40-6Vol 40 · Issue 6Issue 40-5Vol 40 · Issue 5

Kiewit Energy – Kearl Lake – Kearl Fine Tailings Treatment

Published April 14, 2014 · Last reviewed November 2, 2026
Kiewit Energy – Kearl Lake – Kearl Fine Tailings Treatment

Contributed by Bermingham Foundation Solutions

In September 2013 Kiewit Energy Canada contacted Louis Fritz P.Eng of Bermingham Foundation Solutions regarding the need for a Piling System capable of handling 36, 30 and 20 inch pipe piles for their upcoming project in Kearl Lake: The Kearl Fine Tailings Treatment Project.

Upon order confirmation in December 2013, Bermingham successfully manufactured 127 Feet of L27 Vertical Travel Leads to pair with a Kiewit owned Manitowoc 999 Crane.  The leads are complemented with two rental Bermingham diesel hammers B5505 and B6505  that are interchangeable on the lead without having to change gate drive centers.  Bermingham designed a multi-hammer hammer-cat specifically for this order so that Kiewit could change between the B5505 and B6505 seamlessly.

This is the second system that Kiewit currently has with Bermingham for the Kearl project.  Kiewit is also renting Bermingham’s HC275 Crane, VTL System and another pair of B6505 and B5505 hammers.

Bermingham successfully delivered this latest system before the end of January, thereby delivering a completely new system in under two months that also contained the December holiday shutdown.

Bermingham is proud of its continued relationship with Kiewit Energy and hopes to pursue more work with Kiewit into the future.