LATEST ISSUES OF PILE BUCKAll issues →
Issue 42-4Vol 42 · Issue 4Issue 42-3Vol 42 · Issue 3Issue 42-2Vol 42 · Issue 2Issue 42-1Vol 42 · Issue 1Issue 41-6Vol 41 · Issue 6Issue 41-5Vol 41 · Issue 5Issue 41-4Vol 41 · Issue 4Issue 41-3Vol 41 · Issue 3Issue 41-2Vol 41 · Issue 2Issue 41-1Vol 41 · Issue 1Issue 40-6Vol 40 · Issue 6Issue 40-5Vol 40 · Issue 5

Bauer Involved in Construction of Frankfurt Residential Quarter Westville

Published August 11, 2021 · Last reviewed November 2, 2026

Contributed by Bauer Spezialtiefbau

Bauer involved in construction of Frankfurt residential quarter WESTVILLE

Frankfurt am Main, Germany – On the west side of the Gallus district of Frankfurt, a residential quarter is being constructed with more than 1,300 apartments, a two-story underground garage, daycare centers as well as commercial and retail units. BAUER Spezialtiefbau GmbH was commissioned by BST Becker Sanierungstechnik GmbH, on behalf of the owner Instone Real Estate, with the construction of an impermeable mixed-in-place (MIP) retaining wall with a single-layer tie back.

Bauer constructs the retaining structure for construction sections WA 5 to WA 7. In total, approximately 12,000 m2 of static retaining wall is being constructed up to a depth of 18 m. “To ensure the possibility of easy dismantling, the top 2 m of the retaining wall is mostly constructed with timber lagging extending approximately 1,200 m2,” explains Bauer Site Manager Arno Schebaum. “For quality assurance of the retaining structure, inclinometer measuring points are set up, anchor load measurement cells are installed and a deformation check is carried out.” In addition, temporary anchors of up to 30 m in length are constructed to tie back the retaining structure. This work involves approximately 5,000 m of drilling. An RG 16 T and an RG 25 S are used for the mixed-in-place work to construct the retaining structure. A KLEMM KR 806 is used for the installation of the anchors.

The advantages of the MIP construction method are the shorter execution time as well as its sustainability, because the building material is produced on-site using the existing soil as an aggregate. This significantly reduces not only the delivery time of the materials, but also the time needed for removal of the excavated material and thus the emission of greenhouse gas.

The work executed by Bauer began in February this year and will continue until August 2021. The new residential quarter WESTVILLE on Kleyerstrasse, on the grounds of the former Avaya site, is expected to be completed by mid-2025.