Issue 42-5Vol 42 · Issue 5Issue 42-4Vol 42 · Issue 4Issue 42-3Vol 42 · Issue 3Issue 42-2Vol 42 · Issue 2Issue 42-1Vol 42 · Issue 1Issue 41-6Vol 41 · Issue 6Issue 41-5Vol 41 · Issue 5Issue 41-4Vol 41 · Issue 4Issue 41-3Vol 41 · Issue 3Issue 41-2Vol 41 · Issue 2Issue 41-1Vol 41 · Issue 1Issue 40-6Vol 40 · Issue 6

Aarsleff Awarded Foundation Contract at Newhaven Port Development

Published June 27, 2019 · 2 min read · Last reviewed November 2, 2026

Contributed by Aarsleff Ground Engineering

Aarsleff Awarded Foundation Contract at Newhaven Port DevelopmentAarsleff Ground Engineering have been awarded the piling contract for a new aggregates processing plant at Newhaven Port in East Sussex.

The development will see a new aggregates processing plant at the Brett Group’s Newhaven East Quay site. The location of the plant will enable ships to unload aggregates which will be turned into building materials. The new plant will also make use of the recently redeveloped Newhaven Marine Sidings, allowing products to be transported via road and rail.

Aarsleff’s piling works include driving 752no. 300mm precast concrete piles of up to 37m lengths for a new storage area and conveyor system to be built. Aarsleff will also install 6no. 339mm diameter piles up to 40m lengths to support a hopper crane on the dock side. Chris Glenn, Aarsleff Ground Engineering’s piling estimator, talked about the conditions and reason for the pile lengths,

“The ground conditions at Newhaven Port consist of clayey fine sand and soft chalk, which means we have to drive piles down to depths in the region of 37m to obtain the required loads. We plan to utilise a crane to install the steel tubular piles for the hopper crane due to site constraints and poor ground conditions.”

Aarsleff carried out previous piling works at Newhaven Port, with the installation of 166no. precast concrete piles for new fuel tanks and steel tubular piles for two Davit crane bases back in 2017.

Aarsleff’s Managing Director Kevin Hague said,

“It is great to be working at Newhaven Port with Brett Group on their new aggregates processing plant. We have a good working relationship with Brett from previous projects, and I hope that it’ll only continue to strengthen.”

Aarsleff expect to commence works on the 24th June using two of its Junttan piling rigs to install the piles over a 10-week programme.