Now Reading
Bauer Constructs Cut-off Wall for Hydroelectric Power Plant in Nepal
Volume 40 Issue 1
Volume 39 Issue 6
Volume 39 Issue 5
Volume 39 Issue 4
issue 39-3
Volume 39 Issue 3
Volume 39 Issue 2
Issue 39-1 - Jan/Feb 2023
Volume 39 Issue 1
Issue 38-6 - Nov/Dec 2022
Volume 38 Issue 6
Issue 38-5 - Sep/Oct 2022
Volume 38 Issue 5
Issue 38-4 - Jul/Aug 2022
Volume 38 Issue 4
Issue 38-3 - May/Jun 2022
Volume 38 Issue 3
Volume 38 Issue 2

Bauer Constructs Cut-off Wall for Hydroelectric Power Plant in Nepal

Sankhuwasabha District, Nepal – The Arun River in Nepal flows from Tibet through the Himalayas into China. Of all Nepalese river basins, it has the largest area covered in snow and ice. A new hydroelectric power plant is currently being constructed on this river, and it is expected to produce up to 900 MW of electricity.

BAUER Engineering India Pvt. Ltd., a subsidiary of BAUER Spezialtiefbau GmbH, was tasked by the Indian company Jaiprakash Associates Limited with the construction of a cut-off wall as part of the project Arun III HEP. The goal is to achieve a seal and reduce seepage water below the upstream cofferdam and in the left and right abutments.

The scope of service provided by Bauer includes the execution of 3,500 running meters of drilling and injection work on the cofferdam. In the granular construction soil, composed of sand, gravel, rubble, and boulders, the pore injections are executed by means of tube-àmanchette and annular grouting.

“Using the pore injections, we are able to fill the pores in the very loose soil with cement slurry and thereby reduce its permeability”, explains Project Manager Satish Kumar. He continues: “Injections require a high degree of quality assurance and quality control. We are able to meet the strict demands thanks to our many years of experience.” In addition to the pore injections, Bauer will also carry out rock grouting in order to fill gaps, fractures, and cavities in the rock.

Due to the remote location in the Himalayas, not only the construction soil poses a challenge, but also logistics. On top of that, the schedule is very tight: this is because snow starts to melt in March, causing the water level in the river to rise and making work more difficult.

A KLEMM KR 909 is being used for the drilling and injection work. The work executed by Bauer started in December 2021 and is expected to be completed by May 2022.

Scroll To Top
NuCore Skyline